Pilot Roll Out Plan

This section covers the following:

Pilot Roll-out Timelines

Milestone
Timeline

MUKTASoft Launch in UAT Environment

19th May

Training and UAT

22nd May - 25th May

Pilot Go-Live (Launch of MUKTASoft in Production Environment)

31st May

Pilot Duration

45 days

Pilot Completion

July 15th

Program and Governance Set-Up Activities

Task
Assignee
Dependency (If any)
Start Date
End Date
Status
Remarks (If any)

II. Kick Off and Governance Set-Up

Meeting to initiate discussion on Pilot Preparation

Prashanth

None

4th April

6th April

Completed

Identification of SPOCs from Department for Pilot

Prashanth

None

4th April

6th April

Completed

Shubhranshu (Functional) + Anil ( Technical)

Identification of SPOCs from 2 ULBs for Pilot Preparation (For logistics support, training, driving data entry, dissemination of IEC material etc. )

Prashanth

None

4th April

6th April

Completed

Subrat - Dhenkanal Madhusmita - Jatani

Communication to Department and ULBs regarding timeline

Shivani

Confirmed with the department. To be additionally notified through a letter

23rd April

2nd May

Completed

Agree on Roles and Responsibilities for Stakeholders

Shivani

To be shared in a letter with the department, department to approve/ suggest modifications

23rd April

27th April

In Progress

Sign off on Pilot Success Metrics

Shivani

To be shared in a letter with the department, department to approve/ suggest modifications

23rd April

3rd May

In Progress

Sign off on Adoption Metrics from Department

Shivani

To be shared in a letter with the department, department to approve/ suggest modifications

23rd April

3rd May

In Progress

Agree on review and monitoring frequency and stakeholders with Department

Shivani

To be shared in a letter with the department, department to approve/ suggest modifications

23rd April

3rd May

In Progress

Agree on review and monitoring frequency and stakeholders with ULBs

Shivani

To be shared in a letter with the department, department to approve/ suggest modifications

23rd April

3rd May

In Progress

Agree on escalation matrix (ULB Level, Department Level)

Shivani

To be shared in a letter with the department, department to approve/ suggest modifications

23rd April

3rd May

In Progress

On-boarding of PMU for supporting adoption and monitoring on-ground

Shivani

Subhranshu, HUDD SPOC to support in executing this

23rd April

3rd May

In Progress

Department in the process of on-boarding an EY team for this

Institution of Help-Desk

Task
Assignee
Dependency (If any)
Start Date
End Date
Status
Remarks (If any)

III. Institution of Help Desk

Set-up of L1 Helpdesk for Go-Live - Identification of Personnel

Arindam

To be executed by the department

15th May

25th May

Not Initiated

Already agreed with the department

Training of Helpdesk Personnel

Nirbhay

Nominated individuals to be made available for training

15th May

18th May

Not Initiated

Setting up of a Ticketing System

Arindam

To be facilitted by eGov team(JIRA free version)

4th May

24th May

Not Initiated

Develop and share an SOP for triaging

Arindam

None

26th Arpil

28th April

Completed

Escalation Matrix for functional/ technical queries

Arindam

None

26th April

28th April

Completed

User Training & UAT Plan

Task
Assignee
Dependency (If any)
Start Date
End Date
Status
Remarks (If any)

IV. User Training & UAT

Creation of Training Plan

Shivani

None

24th April

2nd May

Completed

Venue: SUDA Conference Hall

15th May

18th May

NA

Trainers/ UAT Drivers: Nirbhay and Arindam

15th May

18th May

NA

Facilitators: Sourav, Shivani and Prashanth

15th May

18th May

NA

Master Trainers (~15 members) 1. 5 members from UMC MUKTA team in Bhubaneshwar 2. 2 IT Resources from UMC Head-Office 3. 4 City Mission Managers (CMMs) 4. From HUDD - Anil and Ashutosh 5. 2 MIS Team members nominated to constitute the Helpdesk

15th May

18th May

NA

MUKTASoft Users (~10 members) 1. ULB Employees (EO, JE, AE, ME, MUKTA Team - Implementation Expert, Program Coordinator, Accountant, MIS Team Member) 2. SHG Members (President & Secreatary from 4 SHGs where 2 SHGs will be from Dhenkanal and 2 from Jatani)

15th May

18th May

NA

Devices Required 1. Laptop/ Desktop: Windows Devices with alteast Windows 10 Pro and Chrome browser (latest version) 2. Mobiles: Android Devices with Android 10 for CBOs to download app or phone with Chrome Browser (latest version) for ULB staff to use the app on phone instead of laptop/ desktop

Shubhranshu to support on ground.

15th May

18th May

NA

Training Day1

Availability of Trainees + Required Devices

22nd May

22nd May

NA

9:00 am - 9:30 am Registration

NA

NA

NA

9:30 am -10:30 am Demo

NA

NA

NA

10:30 am - 11:00 am Tea Break

NA

NA

NA

11:00 am - 1:00 pm Hands-on Training Session 1 (Project, Estimate)

NA

NA

NA

1:00 pm -2:00 pm Lunch

NA

NA

NA

2:00 pm - 4:00 pm Hands-on Training Session 2 (Work Order,Muster Roll, Purchase Bill, Payment Advice)

NA

NA

NA

4:00 pm- 4:30 pm Tea Break

NA

NA

NA

4:30 pm- 5: 30 pm Hands-on Training Session 3 (CBO App)

NA

NA

NA

Training Day 2

23rd May

23rd May

NA

9:30 am -11:00 am Hands-on Training continues

NA

NA

NA

11:00 am - 11:30 am Tea Break

NA

NA

NA

11:30 am - 1:00 pm Q & A, Feedback, Preparation for UAT (Test case handouts distributed based on Roles)

NA

NA

NA

1:00 pm - 2:00 pm Lunch

NA

NA

NA

2:00 pm - 4:00 pm UAT Session 1

NA

NA

NA

4:00 pm- 4:30 pm Tea Break

NA

NA

NA

4:30 pm - 5:30 pm UAT Session 2

NA

NA

NA

Training Day 3

24th May

24th May

NA

9:30 am - 11:00 am UAT Session 3

NA

NA

NA

11:00 am - 11:30 am Tea Break

NA

NA

NA

11:30 am - 1:00 pm UAT Session 4

NA

NA

NA

1:00 pm - 2:00 pm Lunch

NA

NA

NA

2:00 pm - 4:00 pm UAT Session 5

NA

NA

NA

4:00 pm- 4:30 pm Tea Break

NA

NA

NA

4:30 pm - 5:30 pm UAT Session 6

NA

NA

NA

Training Day 4

25th May

25th May

NA

9:30 am - 11:00 am UAT Session 7

NA

NA

NA

11:00 am - 11:30 am Tea Break

NA

NA

NA

11:30 am - 1:00 pm UAT Session 8

NA

NA

NA

1:00 pm - 2:00 pm Lunch

NA

NA

NA

2:00 pm - 4:00 pm (Bugs, Enhancements, Feedback Collection and Prioritization)

NA

NA

NA

4:00 pm- 4:30 pm Tea Break

NA

NA

NA

4:30 pm - 6:00 pm Feedback , Quiz on Training and UAT, Closure

NA

NA

NA

Creation of Training Assets (User Manuals, FAQs and Demo Videos)

eGov Team

UMC to Support on Translation & Design

26th April

19th May

In Progress

User Manuals

Nirbhay

26th April

5th May

In Progress

FAQs

Nirbhay

Demo Videos

Nirbhay

11th May

13th May

Not Initiated

Will be ready by Go-Live

Translation and Printing of Training Assets

UMC -Pranati

Assets to be shared with UMC Team as and when completed by us to start translation

6th May

19th May

Not Initiated

Training Delivery and UAT

eGov Team

Trainees and Devices to be available

15th May

19th May

Not Initiated

Facilitate Training

Nirbhay + Arindam

15th May

19th May

Not Initiated

Gather Feedback on Training

Program Team

Feedback Questionnaire to be Translated

19th May

19th May

Not Initiated

UAT Sign-Off

Program Team

19th May

19th May

Not Initiated

Plan Refresher Training (Tentatively 3-4 weeks later )

Program Team

To be planned based on feedback

15th June

17th June

Not Initiated

Change Management Plan

Task
Assignee
Dependency (If any)
Start Date
End Date
Status
Remarks (If any)

VI. Change Management Plan

People / Behavioural Management

Training Plan (Covered in Section IV above)

Shivani

None

26th April

3rd May

Completed

IEC Plan (Covered in Section V above)

Shivani

None

26th April

3rd May

Completed

Incentives

TBD

Officiial notifications to gradually restrict manual practices to 2 ULBs: 1. Only MUKTASoft generated muster rolls will be approved starting July 1st (for projects approved after go-live date) 2. Editing of attendance should be undertaken only for last 2 weeks starting July 15th (for projects approved after go-live) and the window for editing attendance will be limited to 1 week with launch of v1.1

Sourav

To be taken up fate V1.2 launch

Technical Change Management

Gather Feedback After Go-Live (Bi-weekly calls with CBOs and ULB members from 2 ULBs)

eGov Team

None

8th June

15th July

Not Initiated

Ongoing Activity. Reflected in the Meeting Cadence

Plan for Enhancements/ Upgrades/ Changes (Detailed Technical Effort to be Planned)

Arindam

Once we have inputs from UAT this can be estimated

26th May

30th May

Not Initiated

Cadence for Identifying and Prioritizing Enhancements

Shivani

None

23rd April

3rd May

Completed

Reflected in the Meeting Cadence

Adoption Plan

Task
Assignee
Dependency (If any)
Start Date
End Date
Status
Remarks (If any)

VII. Adoption Plan

Creation of User Training Plan (Covered in Section IV above)

Shivani

None

24th April

2nd May

Completed

Institution of Help Desk Institution (Covered in Section III above)

Arindam

Support required from department to set up tool, resources.

26th April

26th May

In Progress

Included as part of Issue Resolution Matrix; Agreement taken from the department on this

Establish Program Governance Structure

Shivani

To be shared in a letter with the department, department to approve/ suggest modifications

23rd April

3rd May

Completed

Establish Review Cadences

Shivani

To be shared in a letter with the department, department to approve/ suggest modifications

23rd April

3rd May

Completed

Incentives

TBD

Roll -Out Dashboard / Scripts

Arindam

To be initiated on finalization of success metrics

8th May

15th May

Not Initiated

Travel Plan

Function
Member
W-2(1st May)
W-1(15th May)
W1(22nd May)
W2 (29th May)
W3 (5th June)
W4 (12th June)
W5 (19th June)
W6 (26th June)
W7 (3rd July)
W8 (10th July)

Product

Nirbhay

M,T,W,Th

Th,F

M,T,W,Th

CK

To be planned if necessary

Implementation

Arindam

M,T,W,Th

Th,F

M,T,W,Th

Manas

To be planned if necessary

Program

Shivani

M,T,W,Th

M,T,W

Prashanth

M,T,W,Th

M,T,W

Satwinder

To be planned if necessary

Sourav (Based in Dhenkanal W2 onwards)

M,T,W,Th, F

M,T,W,Th, F

M,T,W,Th, F

M,T,W,Th, F

M,T,W,Th, F

Others

Abhishek Rout (Based in Jatani W2 onwards)

To be planned if necessary

Pradip

Sankar