EMP: Create Time Extension

Creating a time extension request by employee

Context

A work order is created for an approved estimate in order to award the work to CBO. CBO starts the work to complete it within a given time period.

In case the organization comes to know that they are not in a position to complete the work within the given time frame due to various reasons, they need to inform the same to officer-in-charge of the project and apply for a time extension which is then subject to approval/ cancelling of work order based on the analysis done by the ULB.

Scope

Request for time extension can be directly raised by CBO using the mobile application and by the officer-in-charge of the project on behalf of CBO using a web application. Once a request is raised it goes for verification and approval.

Home > Work Orders > Inbox > Search Work Order > View Work Order > Request Time Extension (From Action Menu)

Details

  1. Work order to be revised to extend the completion period.

  2. The request to revise the work order for the extension of time can be created by the CBO/officer-in-charge.

#
Field
Data Type
Required
Description

1

Work order number

Display Only

NA

Work order no.

2

Project ID

Display Only

NA

Project ID of the project.

3

Project sanction date

Display Only

NA

Date of the proposal from the project.

4

Project name

Display Only

NA

Project name

5

Project description

Display Only

NA

Project description

8

Work Order Details

Tab

9

Name of CBO

Display Only

NA

The name of the CBO as per original WO.

10

CBO ID

Display Only

NA

The CBO ID as per original WO.

11

Role of CBO

Display Only

NA

The role of the CBO IA/IP as per original WO.

12

Name of the officer in-charge

Display Only

NA

Name of officer in-charge as per original WO.

13

Designation of officer in-charge

Display Only

NA

Designation of officer in-charge as per original WO.

14

Project completion period

Display Only

NA

Number of days work to be completed as per original WO.

15

Work Start Date

Display Only

NA

Work start date as per original WO.

16

Work End Date

Display Only

NA

Work end date as per original WO.

17

Work order amount

Display Only

NA

Total estimated cost as per original WO.

18

Extension requested

Numeric

Y

Time requested to extend in days.

19

Reason for Extension

Text-area

Y

The reason of time extension to be captured here, it should not be more than 250 characters.

20

Terms and Conditions

Display Only/ Tab

NA

Terms and conditions as per original WO.

Validations

On Request Time Extension

  1. In case the first muster roll is pending to submit for approval.

Time extension request can not be created. Please ensure that no muster roll is pending for submission.

2. In case the first muster roll itself is not created.

Time extension request can not be created. Please ensure that the first muster roll is submitted for approval.

3. In case a project closure request is already created.

Time extension request can not be created. A closure request has already been created for the selected project.

Notification

Not applicable.

Action

On submit, create and forward workflow pop-up window is displayed.

On Create and Forward,

  1. The success page is displayed.

  2. The time Extension request number is generated as per the specified format. TE/2022-23/000021.

  3. The time extension request is forwarded to the verifier in the workflow.

User Interface

https://www.figma.com/file/M2P3O9WlKtxuLCjQKxLLDg/DIGIT-Works?type=design&node-id=6705-47564&t=8SVsHQhTGuDo3QW4-4

Acceptance Criteria

  1. Modification of work order is allowed to extend the time.

  2. A time extension request number is generated to identify the request.

  3. The link between original and revised work orders is maintained.

Last updated

All content on this page by eGov Foundation is licensed under a Creative Commons Attribution 4.0 International License.