Product Requirements Document v2.0

Introduction

Mukhyamantri Karma Tatpara Abhiyan Yojana ( MUKTA Yojana) is a government scheme and This scheme is helpful for the poor urban people, which leads to the rising of the employment rate of the state. This document is prepared to detail out the specification MUKTASoft v2.0.

MUKTASoft aims to improve the overall scheme efficiency of MUKTA by identifying & providing equal job opportunities to the urban poor, construct environment-friendly projects, develop local communities and slums & plan better for upcoming years.

Purpose

The purpose of this document is to give a detailed description of the requirements for the MUKTASoft v2.0. It will illustrate the purpose and complete declaration for the development of the system. It will also explain system constraints, interface and interactions with other external applications. This document is primarily intended to define the scope of the version v2.0 and propose to the stakeholders for its approval and as a reference for developing the next version of the system for the development team.

Definitions, Acronyms & Abbreviations

JE

Junior Engineer

ME

Municipal Engineer

EO

Executive Officer

MC

Municipal Corporation

DDO

Drawing and Disbursing Officer

SOR

Schedule of Rates

WO

Work Order

PO

Purchase Order

MB

Measurement Book

Source of Information

1. MUKTA FRS

2. Field Visit to Dhenkanal and Jatni ULBs [21st & 22nd June 2023]

In Scope

  1. Schedule of Rates

    1. Material

    2. Machinery

    3. Labour

    4. Works (Includes Material, Machinery, Labour)

  2. Detailed Estimate

  3. Revise Estimate

  4. Detailed Measurement Book

  5. Muster roll and purchase bill validations

Scope of v2.1, v2.2, v2.3, v2.4 and v2.5

  1. Rate Analysis

  2. Estimate Template

  3. Analysis Statements

    1. Labour Analysis

    2. Material Analysis

    3. Machinery Analysis

  4. Cancel Work Order

  5. Utilization Statements

    1. Labour Utilization Statement (Quantity of Work Completed)

    2. Material Utilization Statement

    3. Machinery Utilization Statement

  6. Project Closure

  7. Dashboard Enhancements

Functional Details

Actors

Users/FeaturesStateULB

Create SOR

Yes

No

Search SOR

Yes

Yes

View SOR

Yes

Yes

Modify SOR

Yes

No

Add/Modify Rate

No

Yes

Schedule of Rates

The basic rate of material, labour, and machinery is decided by the state public works department which would be the same for a group of ULBs and then the final cost of SORs would vary from ULB to ULB based on the Conveyance and Royalty Charges applicable for the ULB.

Units of Measurement

  1. CUM - Cubic Meter

  2. QNTL - Quintal

  3. MT - Metric Ton

  4. NOs - Numbers

  5. KG - Kilogram

  6. LTR - Liter

  7. SQM - Square Meter

  8. HOUR - Hour

  9. MTR - Meter

  10. KL - Kilo Liter

SOR Heads

  1. Material Basic Rate

  2. Labour Basic Rate

  3. Machinery Basic Rate

  4. Exploration Mineral Fund

  5. District Mineral Fund

  6. Conveyance

  7. Royalty

  8. Labour Cess

SOR Type

There are a total of 4 types of SOR.

S.No.CodeType

1

M

Material

2

L

Labour

3

E

Machinery

4

W

Works

SOR Sub Type

The SOR of type works are grouped into various sub-types as given below.

S.No.CodeSub Type

1

EW

EARTH WORK

2

CC

CEMENT CONCRETE

3

RC

RCC WORK

4

MB

MASONRY BRICK WORK

5

MS

MASONRY STONE WORK

6

PL

PLASTERING

7

WC

WHITE & COLOUR WASHING

8

FL

FLOORING

9

PA

PAINTING

10

RD

ROAD WORK

11

WD

WOOD WORK

12

RF

ROOFING

13

DI

DISMANTLING

14

PB

PAVER BLOCK

15

SC

SITE CLEARANCE

16

PF

PILE FOUNDATION

17

IW

IRON WORK

18

BI

OTHER BUILDING ITEMS

SOR Variants

S.No.CodeDescription

1

FN

Excavation in Foundation

2

GF

Ground Floor

3

SF

Second Floor

4

TF

Third Floor

5

PL

Foundation and Plinth

6

SG

Super Structure (GF)

7

SS

Super Structure (SF)

8

ST

Super Structure (TF)

9

BS

Basic

Schedule of Rates

The scheduled items for which the works department publishes the rates are known as the schedule of rates. There are mainly 4 types of items for which schedules of rates are published.

  1. Material - These are the material items which are required to accomplish a work.

  2. Labour - The skilled and unskilled labourers who are required to accomplish the work.

  3. Machinery - These are the equipment which are required to accomplish the work.

  4. Works - The composition of material, labour, and machinery together form a building block for a work.

Create

In MUKTA only a limited set of SORs are being used to estimate a work and initially, only the relevant SOR items are created. The option to create an SOR is provided to help the user take any missing or new SOR into the system as and when needed.

Attributes

S.No.Attribute NameIs Mandatory?Description

1

SOR Type

Yes

Material, Labour, Machinery, Works.

2

SOR Sub Type

Yes

Applicable for SOR type Works only.

3

SOR Variant

No

Applicable for SOR type Works only.

4

Unit of Measurement

Yes

Unit of measurement for the item.

5

Rate Defined for Quantity

Yes

Quantity of items for which basic rate is defined.

6

Description

Yes

Name of item as per the standard definition of OPWD

Rate Details

Optional

7

Effective From

Yes

The date given rate will become effective, it can be a past and future date.

Heads

Grid

To select a head whichever is applicable.

8

Basic Rate

Yes

The basic rate of the item defined by the OPWD

9

Conveyance

No

The conveyance charges applicable based on the distance item is carried.

10

Royalty

No

The royalty amount on the items as per the state mining department.

11

Labour Cess

No

It is applicable for works items only and calculated on Basic + Conveyance + Royalty.

12

Rate

Display

A calculated value.

Mockups

Search SOR

Search SOR provides the option to the user to search an SOR to see the details and modify it to bring the new rates into effect from a well-defined effective date.

Search Criteria

S.No.Field NameData TypeDescription

1

SOR Code

Text

It is system system-generated unique code to identify the SOR uniquely

2

SOR Type

Drop-down

SOR types, the values from SOR Type Master.

3

SOR Sub Type

Drop-down

SOR subtypes, the values from SOR Sub Type Master

4

SOR Variant

Drop-down

SOR variants, the values from Variant master

5

Status

Drop-down

Active/ Inactive

6

Effective From

Date

The rate effective from date

7

Effective To

Date

The rate effective from date

Search Result

The search result always displays the currently effective rates unless the search is for a different effective period.

S.No.Field NameDescription

1

SOR Code

It is system generated unique code to identify the SOR uniquely.

2

SOR Description

It is the description of SOR to describe the SOR.

3

SOR Type

SOR types, the values from SOR Type Master.

4

SOR Sub Type

SOR sub types, the values from SOR Sub Type Master.

5

Status

The status of SOR, Active/ Inactive.

6

Rate

The current effective rate of the SOR.

Mock-ups

View SOR

It enables users to display the details of a SOR and then take the required action from there. E.g. Create Rate Analysis, View Rate Analysis, Modify SOR.

Attributes

S.No.Field NameDescription

1

SOR Code

It is system generated unique code to identify the SOR uniquely.

2

SOR Type

SOR types, the values from SOR Type Master.

3

SOR Sub Type

SOR sub types, the values from SOR Sub Type Master.

4

SOR Variant

SOR variant, the values from the SOR Variant Master.

5

Unit of Measurement

The unit of measurement.

6

Rate Defined for Quantity

The quantity of SOR for which rate is provided.

7

SOR Description

It is the description of SOR to describe the SOR.

8

Status

The status of SOR Active/ Inactive. Active means active for usage.

Rate

The rate section of SOR.

9

Effective From

The date from which the rate is effective.

Heads

10

Basic Rate

Basic rate of the SOR, provided by the state PWD.

11

Conveyance

Conveyance cost defined for the unit of quantity given in SOR.

12

Royalty

Royalty defined for the unit of quantity given in SOR.

13

Labour Cess

The amount of labour cess

14

Total Rate

The final rate of SOR.

Rate History

History of rates which were effective in the past.

15

Serial No.

Serial number of the record.

16

Effective From

The rate effective from date.

17

Rate

The net effective rate.

18

View Details

Button to view the break-up of rate.

19

Actions

  1. Modify SOR/ Add Rate - Applicable to all types of SOR.

  2. Create Rate Analysis - Applicable to Works type of SOR.

  3. View Rate Analysis - Applicable to Works type of SOR.

Mockups

Modify SOR

Modifying SOR enables the user to make the necessary corrections in the details and add the new rate effective from a future date.

Attributes

S.No.Field NameData TypeDescription

1

SOR Code

Display

It is system generated unique code to identify the SOR uniquely.

2

SOR Type

Display

SOR types, the values from SOR Type Master.

3

SOR Sub Type

Display

SOR sub types, the values from SOR Sub Type Master.

4

SOR Variant

Display

SOR variant, the values from the SOR Variant Master.

5

Unit of Measurement

Display

The unit of measurement.

6

Defined for Quantity

Display

The quantity of SOR for which rate is provided.

7

SOR Description

Text

It is the description of SOR to describe the SOR.

8

Status

Drop-down

The status of SOR Active/ Inactive.

Mockups

The screen to modify SOR is almost the same as creating SOR with the limitation mentioned in the above table.

Add/ Modify Rate

Add Rate enables the user to add the new rate effective from a future date.

Attributes

S.No.Field NameData TypeDescription

1

SOR Code

Display

It is system generated unique code to identify the SOR uniquely.

2

SOR Type

Display

SOR types, the values from SOR Type Master.

3

SOR Sub Type

Display

SOR sub types, the values from SOR Sub Type Master.

4

SOR Variant

Display

SOR variant, the values from the SOR Variant Master.

5

Unit of Measurement

Display

The unit of measurement.

6

Defined for Quantity

Display

The quantity of SOR for which rate is provided.

7

SOR Description

Display

It is the description of SOR to describe the SOR.

8

Status

Display

The status of SOR Active/ Inactive.

Rate Details

9

Effective From

Date

The date from which the rate is effective. A future date.

Heads

Grid

It will enable the user to select and add a head applicable.

10

Basic Rate

Text

Basic rate of the SOR, provided by the state PWD.

11

Conveyance

Text

Conveyance cost defined for the unit of quantity given in SOR.

12

Royalty

Text

Royalty defined for the unit of quantity given in SOR.

13

Labour Cess

Display

The amount of labour cess, non editable.

14

Total Rate

Display

The final rate of SOR.

Mockups

The screen to modify SOR is almost the same as creating SOR with the limitation mentioned in the above table.

Detailed Estimate

Following administrative approval of the pre-estimation, a comprehensive detailed estimate is meticulously crafted. This detailed breakdown categorizes the estimate into Schedule of Rates (SOR), Non-SOR, and Other Expenses, with individual quantities calculated through precise measurements for each activity. The detailed estimate provides a heightened level of accuracy in forecasting costs, materials, labor, and machinery necessary for project completion. Moreover, it serves as a crucial tool for tendering and contracting purposes.

Create Estimate

The 'Create Estimate' feature empowers users to generate a comprehensive estimate by utilizing measurements gathered on-site. This functionality includes convenient options such as searching for pre-existing templates and adding Schedule of Rates (SOR) through a dedicated SOR search interface directly on the create estimate page.

Search SOR

  1. SOR Type - Drop-down to select a value for SOR type.

  2. SOR Sub Type - Drop-down to select a value for the SOR sub type.

  3. SOR Variant - Drop-down to select a value.

  4. SOR - Drop-down with incremental/ fuzzy search on code/ description.

Plus Measurements

These are the measurements which are added to the measurement to calculate the quantity of a particular SOR.

Minus Measurements

These are the measurements which are subtracted from the measurement to calculate the quantity of a particular SOR.

Attributes

S.No.Field NameData TypeIs Mandatory?Description

1

Estimate Type

Display

Yes

Estimate type, Original/ Revised.

2

Project ID

Display

Yes

Project ID

3

Project Sanction Date

Display

Yes

Project sanction date

4

Project Name

Display

Yes

Project name

5

Project Description

Display

Yes

Project description

Search SOR - It provides the option to search a SOR and add to the estimate.

SORs

1

Code

Display

Yes

SOR code, unique identifier for each SOR.

2

SOR Description

Display

Yes

SOR description from the SOR master for the selected SOR.

3

Unit

Display

Yes

Unit of measurement

4

Rate

Display

Yes

The rate defined and effective currently.

5

Quantity

Display

Yes

Calculated value out of measurements.

6

Amount

Display

Yes

Calculated value and equal to Qty*Amount.

Measurements

1.1

Sr. No.

Display

Auto

Measurement serial number.

1.2

Type

Drop-down

Yes

Plus/ Minus measurements.

1.3

Name

Text

Yes

The name of the measurement.

1.4

Number (Nos)

Numeric

(6,2)

Yes

No. of items.

1.5

Length (L)

Numeric

(6,2)

Yes

Length measured

1.6

Breadth (B)

Numeric

(6,2)

Yes

Width measured

1.7

Height/ Depth

Numeric

(6,2)

Yes

Depth measured

1.8

Quantity

Display

Yes

Qty = N* L*B*D;

1.9

Total

Display

Yes

Grid total for the quantities of measurements

Analysis

1

Material Cost

Display

Yes

Cost of material out of SORs.

2

Labour Cost

Display

Yes

Cost of labours out of SORs.

3

Machinery Cost

Display

Yes

Cost of machinery out of SORs.

Action

1

Save

Button

Yes

Save the estimate as a draft.

2

Generate Analysis

Button

Yes

Generates the analysis and populates the figures.

3

Submit

Button

Yes

Submit the estimate for verification.

Mockups

Workflow

One additional step to be added in the existing estimate workflow to save the estimate as a draft with the creator of the estimate is incorporated.

#ActionRoleFrom StateTo StateStatus

1

Save as Draft

Estimate Creator

Saved as draft

Drafted

2

Submit

Estimate Creator

Saved as draft

Pending for verification

Submitted

3

Verify and Forward

Estimate Verifier

Pending for verification

Pending for technical sanction

Verified

4

Technical Sanction

Technical Sanctioner

Pending for technical sanction

Pending for approval

Technically Sanctioned

5

Send Back

Estimate Verifier

Pending for verification

Pending for correction

Sent Back

6

Send Back

Technical Sanctioner

Pending for technical sanction

Pending for verification

Sent Back

7

Send Back

Estimate Approver

Pending for approval

Pending for technical sanction

Sent Back

8

Send Back To Originator

<roles having access>

<Current Status>

Pending for correction

Sent Back

9

Edit/ Re-submit

Estimate Creator

Pending for correction

Pending for verification

Re-submitted

10

Approve

Estimate Approver

Pending for approval

Approved

Approved

11

Reject

<any roles having access>

<Current Status>

Rejected

Rejected

Revise Estimate

When the amount of work exceeds up to 10% more from originally estimated amount either due to rates being found insufficient or due to some other reasons, a revised estimate is prepared.

  1. A comparative statement is attached on the last page. It includes reasons for increase in cost in case of each item.

  2. The revised estimate should show the variation of each item of work, its quantity, rate and cost under original and revised.

Once a revised estimate is created, both the estimates can be searched and viewed for details. The original estimate will remain unchanged and reflects the original items and its measurements.

Create

It empowers users to modify measurements for existing Schedule of Rates (SOR) and Non-SOR items, consequently adjusting quantities. Additionally, users can seamlessly incorporate new SOR or Non-SOR items into the estimate. These changes collectively result in the creation of a revised estimate, which undergoes a subsequent approval process."

Workflow

A revised estimate follows the same workflow steps of the original estimate and on approval the changes come into effect.

Search

The same search estimate feature is used to search an revised estimate. Hence there is no change in the search screen.

View

It enables users to view the details of the revised estimate. The view screen is the same as the original estimate screen.

Deviation Statement

A deviation statement is generated for each revised estimate in the PDF form. It is generated with a comparison of the original estimate. The format of the deviation statement is given below.

Attribute

Sr. No.

Field Name

Description

1

SOR Code

SOR Code.

2

SOR Description

SOR item from the estimate.

3

Unit

The unit of measurement

4

Rate

Rate per unit

5

Quantity (Original)

Total quantity required for the given SOR item.

6

Amount (Original)

Amount calculated rate*quantity.

7

Quantity (Revised)

Total quantity required for the given SOR item.

8

Amount (Revised)

Amount calculated rate*quantity.

9

Deviation

Deviation, Less/ Excess/ Nil

10

Total

Total of Amounts for both original and revised.

Mockups

Measurement Book

The measurement book is the most important record. It is the basis of all accounts of quantities of work done, and purchase made and it must contain such a complete record of facts as to be conclusive evidence in the court of law.

It is the basis of all accounts of quantities whether of works done by Contractors or by labourers employed departmentally, or materials received. It is so written the transactions are readily traceable.

MB Recording

All the measurements for the work completed are measured and recorded in the measurement book against each and every BOQ provided in the estimate. Once the complete quantity of the item mentioned in the estimate is consumed in MB the item is considered completed.

MB Process Flow

Create MB

It enables users to capture the measurement of the completed works item (SOR/ Non-SOR) and create a record which becomes the basis of payment for the wage seekers, suppliers and supervisors (CBOs).

Attributes

S.No.Field NameData TypeIs Mandatory?Description

1

Work order number

Display

NA

Work order number

2

Project ID

Display

NA

Project ID

3

Project sanction date

Display

NA

Project sanction date

4

Project Location

Display

NA

Project location

5

Project Name

Display

NA

Project name

6

Project Description

Display

NA

Project description

7

View MB History

Link

NA

To show the measurement history in the format given below.

Measurement History

1

Sr. No

Display

NA

Serial number

2

MB Reference Number

Display

NA

Measurement reference number

3

MB Date

Display

NA

Measurement date

4

MB Period

Display

NA

Measurement period

5

MB Amount

Display

NA

Measurement amount

6

Status

Display

NA

Status of the measurement.

Measurement Period - It has to be the same as muster roll period.

1

From Date

Date

Yes

Muster roll start date.

2

To Date

Date

Yes

Muster roll end date.

SORs

1

Category

Display

Yes

SOR Sub type

2

Code

Display

Yes

SOR Code

3

SOR Description

Display

Yes

SOR description from the SOR master for the selected SOR.

4

Unit

Display

Yes

Unit of measurement

5

Rate

Display

Yes

Rate per unit

6

Quantity

Display

Yes

Quantity calculated from measurement captured.

7

Amount

Display

Yes

Calculated from Rate*Quantity.

Measurements

1.1

Sr. No.

Display

Auto

Serial number of measurement

1.2

Type

Display

Auto

Plus/ Minus from estimate.

1.3

Name

Display

Auto

The name of the measurement from the estimate.

1.4

Number (Nos)

Numeric

(6,2)

Yes

No. of items if the unit of measurement is number.

1.5

Length (L)

Numeric

(6,2)

Yes

Length measured for completed work.

1.6

Breadth (B)

Numeric

(6,2)

Yes

Width measured for completed work.

1.7

Height/ Depth (D)

Numeric

(6,2)

Yes

Depth measured for completed work, allowed up-to 2 decimal places.

1.8

Quantity

Display

Yes

Qty = N*L*B*D; rounded up-to 2 decimal places.

1.9

Total

Display

Yes

Grid total for the quantities of measurements, rounded up-to 2 decimal places.

Non SORs - The above is repeated for Non SORs also.

View Utilization Statements - A link to view the utilization statements in HTML view.

Worksite Photos

Tab

7

Worksite Photo

Upload File

Yes

5 photos JPG and PNG images are supported.

Actions

1

Save as Draft

Button

Yes

Action to save the measurement record as draft.

2

Generate Utilization

Button

Yes

Action to generate measurement statements out of measurements taken.

3

Submit

Button

Yes

Action to submit the measurement book for verification

Mockups

Workflow

The table below illustrates the steps of workflow followed to approve the revised work order.

#ActionRoleFrom StateTo StateStatus

1

Save

MB Creator

Drafted

Drafted

2

Submit

MB Creator

Drafted

Pending for verification

Submitted

3

Verify and Forward

MB Verifier

Pending for verification

Pending for approval

Verified

4

Send Back

MB Verifier

Pending for verification

Pending for correction

Sent Back

5

Send Back

MB Approver

Pending for approval

Pending for verification

Sent Back

6

Send Back To Originator

<any roles having access of action>

<Current Status>

Pending for correction

Sent Back

7

Edit/ Re-submit

MB Creator

Pending for correction

Pending for verification

Re-submitted

8

Approve

MB Approver

Pending for approval

Approved

Approved

9

Reject

<any roles having access>

<Current Status>

Rejected

Rejected

Search MB

It enables users to search and MB recordings which are captured for a period and then sent for verification/ approval.

Search Criteria

S.No.Field NameData TypeDescription

1

Ward

Drop-down

Ward name from the configured data.

2

Project Name

Text

Project name

3

MB Number

Text

MB number

4

MB Reference Number

Text

MB reference number

5

Status

Drop-down

Active/ Inactive.

6

Created From

Date

MB created date

7

Created To

Date

MB created date

Search Result

S.No.Field NameDescription

1

MB Reference Number

MB reference number.

2

MB Number

MB number

3

Project Name

Project name

4

CBO Name

Name of CBO to whom work order is awarded.

5

Status

Status of MB.

6

MB Amount

MB amount.

Mockups

View MB

It enables the users to view the details and workflow status of the measurement book.

Attributes

View measurement book displays all the details related to it as given below.

  1. MB Reference Number

  2. MB Number

  3. Work Order Number

  4. Project ID

  5. Project Sanction Date

  6. Project Location

  7. Project Name

  8. Project Description

  9. Measurement History

    1. Sr. No

    2. MB Reference Number

    3. MB Date

    4. MB Period

    5. MB Amount

    6. Status

  10. Measurement Period

    1. From Date

    2. To Date

  11. SORs/ Non SORs

    1. SOR Category

    2. SOR Code

    3. SOR Description

    4. Unit

    5. Rate

    6. Quantity

    7. Amount

    8. Measurements

      1. Sr. No.

      2. Type

      3. Name

      4. Number (No)

      5. Length (L)

      6. Breadth (B)

      7. Height/ Depth (D)

      8. Quantity

      9. Total

  12. Utilization

    1. Material Utilized(₹)

    2. Labour Utilized (₹)

    3. Machinery Utilized (₹)

  13. Workflow Timelines

Mockups

Last updated

All content on this page by eGov Foundation is licensed under a Creative Commons Attribution 4.0 International License.