Success Metrics
MUKTASoft v2.1
Last updated
MUKTASoft v2.1
Last updated
All content on this page by eGov Foundation is licensed under a Creative Commons Attribution 4.0 International License.
# | Metric | Definition | Target Measure (By Dec 2024) |
---|---|---|---|
1
#Projects Created Vs Projects Approved
Projects Created - Count of the projects created in the MUKTASoft
Projects Approved - Count of the projects which are identified and finalized by the ULB committee upto 1 week before till the completion of pilot.
100% projects out of approved projects
2
#Estimates Approved Vs Projects Created
Estimate approved - Count of estimates approved in the MUKTASoft against a project
Projects Created - Count of the projects created in the MUKTASoft, upto 2 weeks before the completion of pilot.
100% projects out of on-boarded projects
3
#Work Orders Accepted Vs Projects initiated on ground*
Work Order Accepted - Count of work orders issued and accepted by CBOs.
Projects initiated on ground. Count of projects where work has been initiated on ground, as on the date of completion of pi
80% accepted work orders accepted.
4
#Wage seekers engaged
Wage seekers engaged - Count of wage seekers engaged by the CBOs for the work orders accepted , upto 3 weeks before the completion of pilot.
100% wage seekers registered for applicable work orders
5
#Muster Rolls Approved Vs Project Period In Weeks
Muster rolls Approved - Muster roll created and approved.
Project Period (In Weeks) - Total period of all the accepted projects initiated upto 2 weeks before the completion of pilot.
95% muster rolls are approved for all the completed projects.
6
₹Bill Created Vs ₹Bill Paid (INR)
Bill Created - Total value of bills created and due for payment Bill Paid - Total value of bills cleared payments
100% of value of bills created
7
₹Works Completed as per MB Vs ₹Bill Created
Work Completed - As per MB the total works completed in monetary terms from approved MB.
Bill Created - The total value of bill created for payments
No deviation more than 5%.