Revise Estimate

When the amount of work exceeds up to 10% more from originally estimated amount either due to rates being found insufficient or due to some other reasons, a revised estimate is prepared.

  1. A comparative statement is attached on the last page. It includes reasons for increase in cost in case of each item.

  2. The revised estimate should show the variation of each item of work, its quantity, rate and cost under original and revised.

Once a revised estimate is created, both the estimates can be searched and viewed for details. The original estimate will remain unchanged and reflects the original items and its measurements.